Higher-than-anticipated costs delaying Coliseum
demolition
Mary E. O'Leary
,
-NEW
HAVEN — First it was safety issues, now it’s money,
but the two are not unrelated.
The latest hurdle to clear before the New Haven
Veterans Memorial Coliseum can come tumbling down is
resolution of unanticipated costs.
Board of Aldermen President Carl Goldfield said Tuesday that inadequate
information provided by the United Illuminating Co. delayed the project and
necessitated extensive engineering consultations to develop a plan to protect
its equipment.
The city and Stamford Wrecking are now in negotiations over who should pick up
the additional costs.
|
While
Goldfield feels UI was at fault for not originally informing the city of what
was needed to protect its underground equipment, he said they don’t appear
legally liable.
"Their requirements for protection were beyond what anyone
anticipated," he said. "If we had gotten the information early on,
the contract would have been more expensive. ... We were given a lower price
because it was anticipated there was less work to do."
Economic Development Director Kelly Murphy would only say the city and Stamford
Wrecking were in negotiations and she hasn’t ruled out a "fall"
deadline for imploding the Coliseum.
Al Carbone, spokesman for UI, said "this is an
issue between the city of
He said they made their concerns about protecting their equipment beneath the
Coliseum and its parking garage "well known" starting last summer.
But by that point, the contract had already been approved.
UI requested technical impact studies both for the extensive conventional
demolition at the site, as well as for the implosion before it would sign off
on the project in August.
Carbone said they have to follow a detailed protocol,
particularly for events of such magnitude.
The arena portion of the Coliseum was demolished last year and since then
several of the concrete floors of the 1,200 space garage, which sat on top of
the arena, have been taken down, as well as a considerable portion of the steel
skeleton.
Holes for explosives have been drilled into remaining supports and earth and
tires will be used to cushion the implosion, along with a temporary bridge that
will be placed over the most sensitive underground utilities.
It will be all over in 18.5 seconds, once Demolition Dynamics, the firm
subcontracted to do the actual implosion, sets off the explosives.